5 MEP Design Pitfalls We Caught Before Opening a Hotel in the CALA Region
Introduction
Opening a hotel in the CALA (Caribbean and Latin America) region is a high-stakes endeavor, especially when expectations for comfort, sustainability, and reliability are sky-high. But even with international consultants and seasoned contractors on board, some fundamental MEP (Mechanical, Electrical, and Plumbing) design issues often go unnoticed, until commissioning, or worse, after guests arrive.
This article shares five real-world MEP design pitfalls we caught and corrected before the opening of hotels and resorts in the CALA region, helping the owner avoid costly rework and reputational damage.
1. Improper Sizing of Fresh Air and Cooling Systems in Humid Climates
The Issue: In several recent CALA projects, we encountered MEP designs that either undersized or oversized the fresh air and central cooling systems. In some cases, ventilation loads were underestimated, assuming minimal door/window use. In others, the designers tried to “play it safe” and grossly oversized the chilled water plant, leading to inefficient operation, short cycling, and unnecessary capital cost.
How We Caught It: Our team reviewed local climate data (wet-bulb temps), occupancy patterns, and BMS sequences. By simulating partial occupancy and shoulder seasons, we discovered how oversized equipment created instability in temperature and humidity control.
Best Practices:
- Don’t assume “bigger is better.”
- Validate load calculations with real weather data and guest behavior.
- Coordinate DOAS and chilled water systems.
- Use variable-speed components and proper control logic.
- Let energy modeling guide actual design decisions.
2. Overlooking Critical Plumbing Protections: Water Quality, Cross-Contamination, and Venting
The Issue: Plumbing is often deprioritized until issues surface. We’ve seen improper water softening damage equipment, missing backflow preventers at hose bibbs and laundry injectors, and missing venting or traps that caused odors in guestrooms.
How We Caught It: We walked risers, reviewed specs, compared against local water reports, and inspected vent stacks and traps before drywall.
Best Practices:
- Always review local water analysis.
- Install backflow preventers per IPC/UPC.
- Ensure P-traps and proper venting.
- Coordinate softening levels with operations.
3. Conflicting Electrical Standards: Local Grids vs. Brand Requirements
The Issue: Some CALA countries use 230V/50Hz systems, while U.S.-based brands expect NEC-compliant 120/208V or 277/480V at 60Hz. Mixing both without a plan can create grounding issues, equipment failures, or unsafe installations.
How We Caught It: By comparing one-lines and panel schedules with utility data and brand standards, we identified mismatches and advised clear interface strategies.
Best Practices:
- Confirm utility voltage, phase, frequency, and grounding early.
- Choose a single standard unless dual systems are justified and separated.
- Verify imported equipment compatibility.
- Use isolation transformers or converters as needed.
4. Poorly Designed Domestic Hot Water Systems: No Redundancy, No Balance, and Risk of Scalding
The Issue: Many systems can’t deliver hot water in under 10 seconds to all fixtures, or they overheat at the source. Some lack backup heating, others have unbalanced loops.
How We Caught It: We reviewed riser diagrams, checked for missing TMVs and balancing valves, and tested delivery times during commissioning.
Best Practices:
- Design for redundancy.
- Balance loops and install TMVs.
- Ensure delivery to any fixture within 10 seconds.
- Use temperature monitoring for control.
5. Poor Maintenance Planning: No Roof Access, No Isolation Valves, Big Headaches
The Issue: Too often, roof units have no safe access, and piping systems lack isolation valves. One minor leak can disrupt an entire wing.
How We Caught It: We reviewed access paths and piping diagrams, and walked the site to confirm.
Best Practices:
- Provide code-compliant rooftop access.
- Ensure clearance around equipment.
- Add isolation valves at all major branches.
- Involve operations teams during design.
Conclusion
Catching these MEP issues early saved time, avoided rework, and protected the guest experience. All hotels demand more than compliance—they require real coordination across MEP, architecture, interiors, and operations. Early, practical reviews are the best way to build it right the first time.
References
- ASHRAE Standard 62.1 – Ventilation for Acceptable Indoor Air Quality
- CIBSE Guide A – Thermal Comfort and Ventilation in Buildings
- International Plumbing Code (IPC) 2021 Edition
- NFPA 70 – National Electrical Code (NEC), Article 110
- IEC Standards for Electrical Installations – European Norms (230V/50Hz, TN-S, TT Systems)
- Manufacturer service manuals (e.g., Daikin, Trane, Mitsubishi)
- LEED v4.1 Hospitality Rating System – Energy & Atmosphere, Indoor Environmental Quality